| Project dates: | |
| Planning Started | May 15, 2011 |
| Subdivision Approval | June 30, 2011 |
| Preliminary design complete | July 17, 2011 |
| Tree Removed | August 23, 2011 |
| Contract Signed | September 20, 2011 |
| Plans Complete | September 26, 2011 |
| Plans Approved | October 6, 2011 |
| Ground Breaking | October 10, 2011 |
| Foundation/Grading Complete | October 22, 2011 |
| Floor/Driveway Complete | October 25, 2011 |
| Roof Complete | November 5, 2011 |
| 1st Inspection Passed | November 8, 2011 |
| Final Inspection Passed | November 22, 2011 |
My initial Ideas/Drawings/Pics to Contractor(s)
click on images for larger view